ARTICLE

Design documentation deficit in public infrastructure: A mixed-methods analysis of compliance, coordination, and lifecycle management in Nepal’s irrigation projects

Sadikshya Dhakal1,2 ,  Subash Kumar Bhattarai1,3*
Show Less
1 Construction Management, Center for Postgraduate Studies, Nepal Engineering College, Pokhara University, Bhaktapur, Bagmati , Nepal
2 Department of Water Resources and Irrigation, Kathmandu, Bagmati , Nepal
3 Construction Engineering and Management, Institute of Engineering, Pulchowk Campus, Tribhuvan University, Kathmandu, Bagmati , Nepal
Received: 27 June 2026 | Revised: 1 August 2026 | Accepted: 18 August 2026 | Published online: 10 September 2026
© 2026 by the Author(s). This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution -Noncommercial 4.0 International License (CC-by the license) ( https://creativecommons.org/licenses/by-nc/4.0/ )
Abstract

This study was conducted as part of the first author’s Master’s research in Construction Management at Nepal Engineering College, with the corresponding author serving as supervisor. This study provides a comprehensive, evidence-based diagnosis of design documentation management practices in public lift irrigation projects in Nepal. Employing a sequential mixed-methods approach, the research integrates a systematic document review of 50 projects, surveys of 96 stakeholders, comprising 50 contractor representatives and 46 Department of Water Resources and Irrigation engineers, and key informant interviews. Analytical techniques include descriptive statistics, Kendall’s Tau correlation, mean response analysis, artificial neural networks (ANNs) for predictive modeling, relative importance index (RII), and thematic analysis using NVivo software. A significant “compliance paradox” was identified: while most stakeholders perceived the design documentation as adequate, no project achieved 100% compliance, with critical design artifacts such as operation and maintenance manuals and quality assurance plans consistently missing. External regulatory factors emerged as the most powerful determinant of design documentation quality (100% normalized importance from ANN), followed by human resource capacity (72%). Inadequate design documentation was directly linked to project delays (54.2% of respondents) and cost overruns (43.8%), while adequate documentation most significantly improved stakeholder coordination (RII = 0.817). The study proposes an actionable five-point blueprint for design process reform: standardized protocols, mandatory training, dedicated documentation officers, Electronic Document Management Systems, and enhanced stakeholder coordination. This paper is the first to provide a comprehensive mixed-methods investigation of design documentation management in Nepal’s public irrigation sector, contributing to design innovation for sustainable infrastructure development in resource-constrained settings.

Keywords
Design documentation
Compliance management
Design coordination
Mixed-methods research
Infrastructure lifecycle management
Sustainable infrastructure design
Funding
None.
Conflict of interest
The authors declare they have no competing interests.
References
  1. Chappell D, Powell-Smith V. Building contract claims. Oxford, UK: Wiley-Blackwell; 2005. doi: 10.1002/9780470759325
  2. Project Management Institute. A guide to the project management body of knowledge (PMBOK® guide), 7th ed. Newtown Square, PA, USA: Project Management Institute; 2021.
  3. Kerzner H. Project management: A systems approach to planning, scheduling, and controlling, 12th ed. Hoboken, NJ: Wiley; 2017.
  4. Nepal, Office of the Auditor General. Preliminary Audit Findings of DWRI for the projects IRBIWRMP. Kathmandu: Office of the Auditor General; 2024.
  5. Love PED, Irani Z, Edwards DJ. A Rework Reduction Model for Construction Projects. IEEE Trans Eng Manage. 2004;51(4):426-440. doi: 10.1109/TEM.2004.835092
  6. Duy Nguyen L, Ogunlana SO, Thi Xuan Lan D. A study on project success factors in large construction projects in Vietnam. Eng Constr Archit Manag. 2004;11(6):404-413. doi: 10.1108/09699980410570166
  7. Fisk ER, Reynolds WD. Construction project administration, 10th ed. Upper Saddle River, NJ: Pearson, 2013.
  8. Hughes W, Champion R, Murdoch J. Construction Contracts. London: Routledge; 2015. doi: 10.4324/9781315695211
  9. PPMO/GoN. Standard Bidding Document (SBD-1S2E): Works (Without Prequalification), Single Stage Two Envelope Bidding Process, 2025. Accessed June 15, 2026. https://www.ppmo.gov.np/
  10. Eastman C, Teicholz P, Sacks R, Liston K. BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers, 2nd ed. Hoboken, NJ: Wiley; 2018.
  11. Silva GA, Warnakulasooriya BN, Arachchige B. Criteria for Construction Project Success: A Literature Review In: 13th International Conference on Business Management (ICBM). University of Sri Jayewardenepura, Sri Lanka; 2016. doi: 10.2139/ssrn.2910305
  12. Obasanjo Olubukola A, Babalola O, Waheed Adeyemi K. A Review of Importance of Construction Documents on Project Delivery. IJLTEMAS. 2024;XIII(IV):28-41. doi: 10.51583/IJLTEMAS.2024.130405
  13. Alshibly H, Chiong R, Bao Y. Investigating the Critical Success Factors for Implementing Electronic Document Management Systems in Governments: Evidence From Jordan. Inf Syst Manag. 2016;33(4):287-301. doi: 10.1080/10580530.2016.1220213
  14. Jacques de Sousa L, Poças Martins J, Sanhudo L. Predicting construction project compliance with machine learning model: case study using Portuguese procurement data. ECAM. 2024;31(13):285-302. doi: 10.1108/ECAM-09-2023-0973
  15. Melzner J, Zhang S, Teizer J, Bargstädt HJ. A case study on automated safety compliance checking to assist fall protection design and planning in building information models. Constr Manag Econ. 2013;31(6):661-674. doi: 10.1080/01446193.2013.780662
  16. Ashworth A, Hogg K, Higgs C. Willis’s practice and procedure for the quantity surveyor, 13th ed. Oxford, UK: Wiley-Blackwell; 2013.
  17. Bhattarai SK, Rayamajhi L, Lamichhane S, Arayal S. Navigating Delays: A Comprehensive Study of Public Building Retrofitting Projects in Kathmandu Valley. JUTEC Eng Manag. 2024;2(01):37-52. doi: 10.36344/utecem.2024.v02i01.004
  18. GON/PPMO. Public Procurement Act, 2063 (2007), 2017. Accessed June 15, 2026. https://ppmo.gov.np/
  19. Cheng T, Teizer J. Real-time resource location data collection and visualization technology for construction safety and activity monitoring applications. Autom Constr. 2013;34:3-15. doi: 10.1016/j.autcon.2012.10.017
  20. Sospeter NG. A categorization of factors affecting quality of design documentation in Tanzanian construction projects. J Eng Des Technol. 2025;23(1):228-248. doi: 10.1108/jedt-02-2023-0040
  21. Govender N, Laryea S, Watermeyer R. Blueprint to Success: Project Managers’ Perspectives on Key Factors Influencing Construction Document Quality in South Africa. J Constr Eng Manag. 2025;151(11). doi: 10.1061/JCEMD4.COENG-16710
  22. Projul. Construction documentation best practices. 2024. Accessed June 15, 2026. https://projul.com/blog/construction-project-documentation-guide/
  23. ASEE, “Managing Project Documentation Across Multiple Regulatory Standards,” American Society for Engineering Education, 2024. Accessed June 15, 2026. https://asee.io/blog/managing-project-documentation-across-multiple-regulatory-standards/
  24. Bhattarai SK, Silwal N, Sharma M, Lohani A, Kafle M. Integrated hybrid NSGA-III–MOPSO model for sustainable time–cost optimization in residential building construction in Nepal. Asian J Civ Eng. 2026;27:3547-3564. doi: 10.1007/s42107-026-01682-y
  25. Buzauova TM, Yelubayeva AN, Toleubayeva SB. Assessing the Impact of Making Adjustments to Design Documentation on the Production Process. Mater Mech Eng Technol. 2024;4:84. doi: 10.52209/2706-977X_2024_4_84
  26. Sibanda M, Schellnack-Kelly I. Perceptions Regarding the Use of Digital Records in Zimbabwe’s Public Sector. Mousaion South Afr J Inf Stud. 2025. doi: 10.25159/2663-659X/17326
  27. Neupane U, Jaisi BP. An assessment of record keeping practices at construction sites: Nepalese perspectives. Rec Manag J. 2025;35(3):277-295. doi: 10.1108/RMJ-06-2024-0014
  28. Mayouf M, Damra T. Smooth drive or rough road? The role of ISO 19650 in developing countries. Constr Manag. Accessed June 15, 2026. https://constructionmanagement.co.uk/smooth-drive-or-rough-road-the-role-of-iso-19650-developing-countries/
  29. Nepal S, Neupane N, Koirala S, et al. Integrated assessment of irrigation and agriculture management challenges in Nepal: An interdisciplinary perspective. Heliyon. 2024;10(9):e29407. doi: 10.1016/j.heliyon.2024.e29407
  30. Shrestha M, Subedi S, Giri OP, Alagirisamy M. Assessing Awareness of Building Information Modeling (BIM) among AEC Professionals in Nepal. Eng Technol Appl Sci Res. 2024;14(6):18973-18980. doi: 10.48084/etasr.9098
Share
Back to top
Design+, Electronic ISSN: 3060-8953 Published by AccScience Publishing